• Construction Activities Look-Ahead

    Updates made: (1/21/21) 

    Construction Activities Look-Ahead

    • Begin Installing Finishes on 2nd Floor
    • Complete MEP Rough installation in Gym/Auditorium
    • Install “Dancefloor” in auditorium to complete overhead work
    • Setting of Rooftop Equipment including RTUs, Fans and Pumphouse

    Recent Milestones 

    • Substantial Completion of Skylight Installation
    • Substantial Completion of the Breakout Spaces structural Framing
    • Drywall installation is progressing nicely in the classrooms/corridor and has also started in the atrium high soffits. Interior mockups have been discussed between members of the project team to begin putting the “finishing touches” on the building.
    • On the roof, the mechanical curbs are currently being set. This will allow the large roof top units to be installed. These units will be used to provide and control the HVAC services to the building.
    • As the structural framing for the breakout space is complete, the MEP Rough Installation process has begun and the project team is finalizing the aesthetic details of the spaces to give them the signature look as some of the focal points of the building.

    COVID 19

    Ongoing:

    • Per Governor Baker’s Order, issued March 23rd and updated on March 31st, construction has been designated as an essential service. The site remains open, and construction is continuing during the COVID-19 pandemic. 
    • Consigli has been proactive in our response, placing additional procedures and safety measures in place that adhere to the CDC Guidelines and the construction guidelines issued from the Commonwealth of Massachusetts to promote worker safety,
    • Impacts to manpower, material availability and fabrication are being monitored on a continuous basis, and all efforts are being made to mitigate said impacts.